Lead paint content (skip menu)

Lead paint violations at 565 West 139th Street, Manhattan

HPD lists 15 open lead paint violations at this Hamilton Heights-Sugar Hill building in Manhattan, under Local Law 1. Each order is set out in plain English, newest first.

open lead paint violations
15
of them class C, immediately hazardous
12
apartments named in open orders, plus 2 building-wide
5
newest lead order issued
May 1, 2026
lead orders on record since 2004
48

An order is open while HPD still hasn't accepted a repair, or proof from the owner, for it. Once HPD accepts it, the order is closed. What to do next

Lead orders still open, newest first

All 15 open orders appear below. When one day's order covers several apartments, those apartments share a row, and each one is named.

ApartmentWhat HPD orderedClassWhereIssued
23Peeling lead paint to fix (order 617)Owner given more timeC, immediately hazardous1st door frame from south at west wall, 1st window frame from north at east wall in the 3rd room from east at southMay 1, 2026
23Peeling lead paint to fix (order 617)Owner given more timeC, immediately hazardous1st door frame from east at south wall, 1st window frame from west at north wall in the 3rd room from east at northMay 1, 2026
23Peeling lead paint to fix (order 617)Owner given more timeC, immediately hazardous1st closet from east at south wall door frame in the private hallwayMay 1, 2026
23Peeling lead paint to fix (order 617)Owner given more timeC, immediately hazardousBaseboard at north wall, 1st window frame from west at north wall in the 1st room from east at northMay 1, 2026
23Peeling lead paint to fix (order 617)Owner given more timeC, immediately hazardous1st door frame from west at north wall in the bathroomMay 1, 2026
23Peeling lead paint to fix (order 624)Inspector could not get in to re-checkC, immediately hazardous1st door frame from south at west wall in the 4th room from eastApr 24, 2026
23Peeling lead paint to fix (order 617)Inspector could not get in to re-checkC, immediately hazardous1st door frame from east at south wall in the 2nd room from east at northApr 24, 2026
23Peeling lead paint to fix (order 617)Inspector could not get in to re-checkC, immediately hazardousNorth wall in the 1st room from east at northApr 24, 2026
23Peeling lead paint to fix (order 617)Inspector could not get in to re-checkC, immediately hazardous1st door frame from west at north wall in the bathroomApr 24, 2026
3 apartments44, 21, 32Vacant-apartment lead work not proven (order 623)B, hazardousThe whole apartmentNov 19, 2024
BuildingYoung children: tenants not asked, or no lead check (order 619)C, immediately hazardousYearly tenant noticeNov 12, 2024
BuildingLead records not handed to HPD (order 620)C, immediately hazardousBuilding paperworkNov 12, 2024
64Peeling lead paint to fix (order 617)Not fixed when re-checkedC, immediately hazardousPlace not named in the orderJun 6, 2018

Unless a row says otherwise, each open order here still reads "notice sent to the owner". For HPD Online, the building ID numbers are BIN 1061727, BBL 1020710005. Open HPD Online

Your next steps

  1. Keep children away from peeling paint. Wash hands, toys, pacifiers, window sills and floors often, and keep children away from rooms where repair work makes dust. Don't sand, scrape or repaint old paint yourself, because that creates lead dust.
  2. Get your child tested. If you think your child was exposed, get a blood lead test from the doctor now. At age 1, and once more at age 2, New York also requires the test. How the test works
  3. Put your complaint in writing. Tell your landlord about the peeling paint, and whether a child under age 6 lives at 565 West 139th Street. Free letters in English and Spanish
  4. Report the problem to HPD. Call 311, or report it online, about peeling paint or repair work that makes dust. Filing is free, and your immigration status doesn't matter.
  5. Child tested high for lead? Follow the doctor's plan for retesting, then talk to a lead paint lawyer about the building's record: call (888) 503-5930.

These lead orders in plain English

Local Law 1 of 2004 is the city's lead paint law, and these orders were issued under it. Lead paint is presumed in buildings built before 1960, and owners get extra duties for apartments where a child under 6 lives.

  • 10 open: peeling lead paint to fix. The paint here contains lead, or is presumed to, and it is peeling or sits on damaged surfaces. Repairing it is the owner's job, using lead-safe work methods.
  • 3 open: vacant-apartment lead work not proven. While the apartment sat empty, the owner had to make its doors, windows and floors lead-safe, then prove that to HPD. The proof isn't there.
  • 1 open: young children: tenants not asked, or no lead check. The owner failed to send the yearly notice asking whether the apartment has a child under 6, or failed to check for lead hazards.
  • 1 open: lead records not handed to HPD. The building's lead paint records, covering notices, inspections and repairs, were requested by HPD, but the owner didn't send them within 45 days.

HPD uses class C for a condition that is immediately hazardous. A closed order is one where HPD accepted a repair, or proof from the owner. Of the lead orders here, 33 are closed.

Lead orders here, year by year

  1. 20043
  2. 200513
  3. 20103
  4. 20116
  5. 20188
  6. 20211
  7. 20245
  8. 20269
Closed lead orders (33)
ApartmentWhat HPD orderedClassIssuedClosed
64Peeling lead paint to fixCJun 6, 2018May 20, 2026
64Peeling lead paint to fixCJun 6, 2018May 20, 2026
64Peeling lead paint to fixCJun 6, 2018May 20, 2026
64Peeling lead paint to fixCJun 6, 2018May 20, 2026
64Peeling lead paint to fixCJun 6, 2018May 20, 2026
64Peeling lead paint to fixCJun 6, 2018May 20, 2026
64Peeling lead paint to fixCJun 6, 2018May 20, 2026
53Peeling lead paint to fixCApr 27, 2021Jan 25, 2022
54Peeling lead paint to fixCApr 27, 2005Aug 21, 2017
54Peeling lead paint to fixCApr 27, 2005Aug 21, 2017
54Peeling lead paint to fixCApr 28, 2005Aug 21, 2017
20Peeling lead paint to fixCJan 18, 2005Jul 31, 2017
21Peeling lead paint to fixCNov 23, 2004Jun 13, 2017
21Peeling lead paint to fixCNov 23, 2004Jun 13, 2017
21Peeling lead paint to fixCNov 23, 2004Jun 13, 2017
21Peeling lead paint to fixCApr 4, 2011Jun 13, 2017
21Peeling lead paint to fixCApr 4, 2011Jun 13, 2017
54Peeling lead paint to fixCFeb 8, 2005May 25, 2017
54Peeling lead paint to fixCFeb 8, 2005May 25, 2017
54Peeling lead paint to fixCFeb 8, 2005May 25, 2017
54Peeling lead paint to fixCFeb 8, 2005May 25, 2017
54Peeling lead paint to fixCFeb 8, 2005May 25, 2017
54Peeling lead paint to fixCFeb 8, 2005May 25, 2017
54Peeling lead paint to fixCFeb 8, 2005May 25, 2017
54Peeling lead paint to fixCFeb 8, 2005May 25, 2017
54Peeling lead paint to fixCFeb 8, 2005May 25, 2017
41Peeling lead paint to fixCJan 11, 2010Apr 12, 2017
41Peeling lead paint to fixCMar 26, 2010Apr 12, 2017
41Peeling lead paint to fixCMar 26, 2010Apr 12, 2017
41Peeling lead paint to fixCApr 11, 2011Apr 12, 2017
41Peeling lead paint to fixCApr 11, 2011Apr 12, 2017
41Peeling lead paint to fixCApr 11, 2011Apr 12, 2017
30Peeling lead paint to fixCJun 13, 2011Apr 12, 2017

A closed order is one where HPD has accepted a repair, or proof from the owner, for it. That doesn't mean the entire building is lead-safe.

Records: HPD's housing violation data, published on NYC Open Data and refreshed monthly; it covers lead paint orders 610 to 626, and the newest lead order anywhere in it is dated October 21, 2026. This page only reads the public record. It is not a medical opinion or a legal finding about the owner.